Roadwork continues this week throughout the area, according to the Georgia Department of Transportation.
Major projects of interest that will likely impact traffic are listed below.
All work subject to change due to weather or other factors. Motorists are
cautioned to reduce their speed while traveling through work zones, pay
attention and watch for workers.
Bryan County
Highway 144 East of Holly Hill Rd. to West of Oxford Dr.
Flagging Operation for Utility Relocation and removal of existing Drainage
Structures
Monday through Wednesday 9 a.m. until 4
p.m.
Highway 17 Ponderosa Rd. and Ending at the Bridge over the Ogeechee
River
Single Lane Closures for Maintenance of Roadway
Monday through Sunday 7 p.m. to 6 a.m.
Highway 144 Widening Project
Rabbit Hill Road Closure near 144 for Drainage Pipe Installation
Detour via Rabbit Hill Road to Port Royal Rd.
Beginning Monday continuing until Installation complete
Bulloch County
Highway 80/Amanda Dr. to Old Lee Field Rd.
Daily Single Lane Closures to Build Roadway
Monday through Saturday from 7 a.m. to 4 p.m.
Chatham County
County Road 787 (Island Expressway) Oatland Island Road to Elba Island
Road
Single Lane closures for utility work and bridge construction
Monday through Friday 9 a.m. until 3 p.m.
Highway US 80 between Stagecoach Road and Old Osteen Road
Lane shift with speed reduction required for Jimmy Deloach Extension Project
Highway 25 Conn/West Bay Street widening project
Traffic shift between West Street and Tuten Street to replace box culvert
Highway 25/Bay Street East of Cleland St. to East of Tuten St.
Single Lane Closure to Pour Concrete Sidewalk
Tuesday through Friday 9 a.m. to 4 p.m.
Highway 21 Fries Rd to Crossgate Rd.MP 11 to MP 11.5
Single Lane Closures for installing a Commercial Driveway and Turn Lane
Monday through Saturday 9 a.m. to 4 p.m.
Highway 17 South of Ponderosa Rd. to South of Ogeechee River Bridge
Single Lane Closures for Milling and Resurfacing
Monday through Sunday 7 p.m. to 6 a.m.
Effingham County
SR 275 @ Rincon-Stillwell Rd. and Long Bridge Rd.
Single Lane Closure to install storm drainage across the road.
Monday through Saturday 9:30 a.m. to 2:30 p.m.